翻訳と辞書
Words near each other
・ Port Penrhyn
・ Port Perry
・ Port Perry Branch
・ Port Perry High School
・ Port Perry Mojacks
・ Port Perry, Pennsylvania
・ Port Perry/Hoskin Aerodrome
・ Port Philip
・ Port Philip, Nova Scotia
・ Port Phillip
・ Port Phillip (disambiguation)
・ Port Phillip Arcade, Melbourne
・ Port Phillip Association
・ Port Phillip Bay (Western Shoreline) and Bellarine Peninsula Ramsar Site
・ Port Phillip Bay Bridge
Port Phillip Channel Deepening Project
・ Port Phillip District
・ Port Phillip District Special Surveys
・ Port Phillip District Wars
・ Port Phillip Gazette
・ Port Phillip Heads Marine National Park
・ Port Phillip Herald
・ Port Phillip Prison
・ Port Phillip Protectorate
・ Port Pipavav
・ Port Pirie
・ Port Pirie (Ellen Street) railway station
・ Port Pirie (Mary Elie Street) railway station
・ Port Pirie Airport
・ Port Pirie City


Dictionary Lists
翻訳と辞書 辞書検索 [ 開発暫定版 ]
スポンサード リンク

Port Phillip Channel Deepening Project : ウィキペディア英語版
Port Phillip Channel Deepening Project

right
right
The Port Phillip Channel Deepening Project (CDP) began on 8 February 2008 to deepen the shipping channels leading to Melbourne, Australia.
The project was to deepen channels in Port Phillip to draught allow greater access for container ships. An estimated A$969 million was to be spent on the works, with $150 million funded by taxpayers. The dredging works were conducted by Dutch company Royal Boskalis Westminster for the Port of Melbourne Corporation (PoMC), a statutory body established by the Victorian Government responsible for the running of the port, at a cost of $500 million and was expected to be completed before 31 December 2009, pending auditor reports and various legal actions against the project. The project was to be conducted under a controversial Public-Private-Partnership.
Operating almost 24 hours a day, the project involved the removal of approximately 22.9 million m3 (810 million cu ft) of sand, fine river silt (including about around 3 million m3 (110 million cu ft) of contaminated sediment) or approximately 1% of the bay by area, assuming the bay has only two dimensions. The material removed was transported to designated "dump sites". According to numerous scientists, community representatives, environmental and community groups, the dredging would disturb marine plant, animal and microbial life through large areas of the bay.〔Dr. Simon Roberts, Monash University, "Submission to the Independent Panel Enquiry: Overview of Nitrogen Cycling Issues"〕〔Dr. Graham Harris, CSIRO, "Report to the Association of Bayside Municipalities on the Channel Deepening Project EES"〕〔http://home.vicnet.net.au/~earthcar/channel%20position.htm〕〔Additional submissions and objections from Earthcare; the VNPA; the Victorian Greens; the Dive Industry of Victoria; and the Australian Peak Shippers' Association who stated that "We are going to be copping the entire cost of deepening the channels without any gain or benefits..."〕
The project has caused significant controversy among many communities throughout the Victorian population, including being strongly opposed by scientists such as biologists and geologists,〔〔 the CSIRO, university academics and scientists including Monash University, and many groups representing the community including the Dive Industry of Victoria, the Victorian Greens, the Australian Peak Shippers' Association, and the Victorian National Parks Association. The amalgamated community group Blue Wedges held public rallies and several pickets from 2004–2008, involving surfers, canoes, kayaks, boats and yachts who put themselves in the path of the dredging ship ''Queen of the Netherlands'', delaying the project for a time. The project eventually began, although under limited conditions, after Blue Wedges won a reprieve in the Federal Court. The limited conditions were stripped from 28 March 2008 after ensuing legal proceedings saw the Blue Wedges case dismissed. Legal costs were pursued by the state government.
In 2009 the Victorian Auditor-General's report was released . The Auditor-General sourced information on what percentage of ships could and could not enter the bay, from the Port of Melbourne exclusively, who had twice previously overestimated the number of ships that could not enter the bay prior to dredging. In contrast, in the Drewry Report, the more accurate calculation of ships that were not loading to full capacity in Melbourne was calculated to be between 10% and 4% -- this Drewry Report was commissioned by the Port of Melbourne Corporation (PoMC previously VCA) in 2001, but was not made accessible to the public until the Victorian Greens obtained it under a Freedom of Information request in 2005—the Drewry Report concluded that, were the channel deepening project to be completely cancelled, the economic loss from this small percentage of ships unable to load to capacity would be in the vicinity of $13 million, rather than the $30 million that had previously been claimed by PoMC. Furthermore, the Drewry Report also concluded that a dredge of 0.5 metres would be sufficient for 96% of vessels, and the PoMC's planned dredge to 2.5 metres depth was "extreme" and "potentially disastrous" as well as expensive and unnecessary. In addition, almost all of the shipping companies that use Melbourne's ports stated that there was no need for dredging or channel deepening in the bay or around the ports .
The government announced the completion of works in November 2009, ahead of schedule and $200 million under budget.
==The project==
The Port Phillip Channel Deepening Project was carried out by Dutch dredging company Royal Boskalis Westminster for the Port of Melbourne Corporation. The PoMC also sought the assistance of Boskalis Australia Pty Ltd, a daughter company of Royal Boskalis Westminster.
Prior to the completion of the works, ships entering the Port of Melbourne were restricted to draught ( at high tide). Larger container ships instead need to carry full loads. The PoMC estimated that in the 2006-07 financial year, 38.5% of ships visiting the port were already potentially affected by draught limitations because the channel did not allow for the extra depth, with this figure rising to 44.3% in the December quarter of 2007.〔 The key objective of the Channel Deepening Project was to address these draught restrictions.

抄文引用元・出典: フリー百科事典『 ウィキペディア(Wikipedia)
ウィキペディアで「Port Phillip Channel Deepening Project」の詳細全文を読む



スポンサード リンク
翻訳と辞書 : 翻訳のためのインターネットリソース

Copyright(C) kotoba.ne.jp 1997-2016. All Rights Reserved.